| 1 | 40 | Energium Administrator | h2. Structure of Redmine |
|---|---|---|---|
| 2 | 2 | Energium Administrator | |
| 3 | 40 | Energium Administrator | # Issue |
| 4 | When a task occurs, Redmine refers to it as an issue. |
||
| 5 | Job type, person in charge, start and end dates, and job progress (%) are recorded, so you can check the progress of the job. |
||
| 6 | # Project |
||
| 7 | It is a unit that groups issues according to job characteristics. |
||
| 8 | 2 | Energium Administrator | |
| 9 | 40 | Energium Administrator | h2. Project structure |
| 10 | 11 | Energium Administrator | |
| 11 | 40 | Energium Administrator | The CS project structure is as follows. |
| 12 | 1 | Energium Administrator | !project.png! |
| 13 | 4 | Energium Administrator | |
| 14 | 41 | Energium Administrator | h2. How to register an issue |
| 15 | 1 | Energium Administrator | |
| 16 | 41 | Energium Administrator | h3. 1. Issue Registration |
| 17 | 5 | Energium Administrator | |
| 18 | 41 | Energium Administrator | # Select a project to register an issue. |
| 19 | 1 | Energium Administrator | !projects.png! |
| 20 | 41 | Energium Administrator | At this time, the project to which the issue will be registered must be a project of equipment unit. |
| 21 | # 'Select the 'Issues' tab. |
||
| 22 | 13 | Energium Administrator | !issues.png! |
| 23 | 41 | Energium Administrator | # Click 'Create New Issue'. |
| 24 | 14 | Energium Administrator | !newissue.png! |
| 25 | 41 | Energium Administrator | # Please refer to the instructions below to register your job. (Items marked with'*' are required fields.) |
| 26 | 15 | Energium Administrator | !issueinfo.png! |
| 27 | 42 | Energium Administrator | *Tracker* : Choose what kind of issue it is. |
| 28 | *Subject* : Enter the title of the issue. |
||
| 29 | *Description* : Enter the details of the issue. |
||
| 30 | *Status* : Enter the progress status of the job. In the case of CS, "Receipt" is the first state, so there is no need to modify it when registering for the first time. |
||
| 31 | *Priority* : This is the importance of this issue. |
||
| 32 | *Assignee* : Assign the person in charge of this task. The person in charge is an item designated by the company, so when an overseas person in charge registers an issue, a person in charge is not designated. |
||
| 33 | *Parent task* : If this task is derived from another task, you can designate a parent task. The process of designating a parent job is as follows. |
||
| 34 | 45 | Energium Administrator | 1) Each issue has a unique number. |
| 35 | 33 | Energium Administrator | !tasknum.png! |
| 36 | 42 | Energium Administrator | 2) If you enter a unique number in the Parent task, the title of the issue is displayed. Please select a title. |
| 37 | 33 | Energium Administrator | !parenttask.png! |
| 38 | 42 | Energium Administrator | *Start date* : Enter the time when this issue occurred. |
| 39 | *Due date* : Enter the time when this issue should be completed. |
||
| 40 | *Estimated time* : Enter the time required to complete this issue (Unit: Hour) |
||
| 41 | *% Done* : Enter the progress of this issue (Unit: %) |
||
| 42 | *Files* : Register attachments. (Up to 1 GB) |
||
| 43 | *Watchers* : : Add members to share the progress of this issue, excluding the person in charge. |
||
| 44 | # After filling in the fields, click the 'Create' or 'Create and add another' button. |
||
| 45 | When you click the 'Create' button, the result of the job registration is displayed as shown in the image below. |
||
| 46 | 34 | Energium Administrator | !new_createMsg.png! |
| 47 | 42 | Energium Administrator | When you click the 'Create and add another' button, a message indicating that the issue has been registered is displayed as shown in the image below, and the previously written contents are initialized and you can enter another issue. |
| 48 | 35 | Energium Administrator | !new_createAnd.png! |
| 49 | 42 | Energium Administrator | # You can check the registered job in the'My page','Issue''Overview','Gantt','Calendar' menu. |
| 50 | 37 | Energium Administrator | * My page |
| 51 | 1 | Energium Administrator | !mypage.png! |
| 52 | 37 | Energium Administrator | * Issue |
| 53 | 1 | Energium Administrator | !new_issue.png! |
| 54 | 37 | Energium Administrator | * Overview |
| 55 | 1 | Energium Administrator | !overview.png! |
| 56 | 37 | Energium Administrator | * Gantt |
| 57 | 38 | Energium Administrator | !gantt.png! |
| 58 | 37 | Energium Administrator | * Calendar |
| 59 | 39 | Energium Administrator | !calendar.png! |
| 60 | 29 | Energium Administrator | |
| 61 | 43 | Energium Administrator | h3. 2. Sub-Issue Registration |
| 62 | 29 | Energium Administrator | |
| 63 | 43 | Energium Administrator | # If you want to register a sub-issue from an already created workbook, select the issue to register the sub-issue from the Issue menu. |
| 64 | 28 | Energium Administrator | !new_issue.png! |
| 65 | 43 | Energium Administrator | # Click 'add' in 'Subtasks'. |
| 66 | 28 | Energium Administrator | !subtasks.png! |
| 67 | 43 | Energium Administrator | # You can see that the unique number of the parent job is entered in 'Parent task'. |
| 68 | 31 | Energium Administrator | !new_subtastk.png! |